Overview

This job aid shows you how to view and override CSU Hire Dates.

Background

  • CHRS does not use the PeopleSoft-delivered original hire date.
  • CHRS uses new custom CSU Hire Dates. The table below describes CSU Hire Dates.
  • A nighty process updates of the CSU Hire Dates to maintain accuracy.
  • Campus administrators can override the CSU Hire Dates to correct them. The nightly process does not update overridden dates.
  • CSU Tenure Dates are maintained by the same process.
CSU Hire Date Definition
CSU Original Hire Date  A single CSU Original Hire Date of a Person to the CSU across all Campus/Business Units
BU Original Hire Date Campus Original Hire Date of a Person to a single Campus/Business Unit of the CSU 
CSU Tenure/Tenure Track Start Date  A single begin date for CSU Tenure/Tenure Track across all Campuses/Business Units of the CSU 
BU Tenure/Tenure Track Start Date Campus Tenure/Tenure Track start date for a particular Campuses/Business Unit of the CSU

View CSU Hire Dates

Step 1: Navigate to CSU Hire Dates.

  • Menu > Workforce Administration > CSU Workforce Admin Process > CSU Date Tracking > CSU Hire Dates
Navbar button

Step 2: Search for the employee: Enter the criteria then click Search.

  • If the search returns only one result, the CSU Hire Dates page opens. Otherwise, select a result to open the page.
Search page

Step 3: On the CSU Hire Dates page, find:

  • CSU Original Hire Date
  • BU Original Hire Date
CSH Hire Dates page

Step 4: On the CSU Tenure Dates page, find:

  • CSU Tenure Start Date
  • BU Tenure Start Date
CSU Tenure Dates page

Override CSU Hire Dates

Campuses can override hire dates if they are incorrect.

Step 1: On the CSU Hire Dates tab, Set the applicable override flag:

  • CSU Original Hire Dt Override
  • BU Original Hire Date Override
Updating CSU Hire dates
  • You can override either date or both at the same time.
  • The override flag signals the nightly process not to change the date.

Step 2: Enter the correct date.

Date field

Step 3: Enter a Comment in the applicable Comments field.

  • You must enter a comment if you override the date.
Comments field

or

Comments field

Step 4: Click Save.

Save button

Override the CSU Tenure Dates

Step 5: On the CSU Tenure Dates tab, Set the applicable override flag:

  • CSU Original Hire Dt Override
  • BU Original Hire Date Override
Updating CSU Tenure Dates
  • You can override either date or both at the same time.
  • The override flag signals the nightly process not to change the date.

Step 6: Enter the correct date.

Date field

Step 7: Enter a Comment in the applicable Comments field.

  • You must enter a comment if you override the date.
Comments field

or

Comments field

Step 8: Click Save.

Save button

End of Article

0 Comments

Add your comment

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Previous Article Update Job with Transactional Front-End (TFE)
Next Article View Transactional Front End (TFE) Transaction Errors