Overview
This article shows CHRS Operations how to close and open calendars. The following operations must be done in the correct order:
Background
CSUPYNLT is a recurrence (run control) and not a JobSet. Peoplesoft has a process each month that clears out the run control which restricts the ability to setup a Job Set. With the Calendar Group having to be manually changed and run each month, a run control (recurrence) is the best course of action.
The reccurrence is controlled by CHRS Operations in regards to setting up, modifying, and stopping the CALC/RECALC and NLT Recurrence for calendar processing.
Each month during the closing of payroll, CHRS Operations must manually Finalize the period. When they do that they have to stop the recurrence and then reestablish the next period (Initialize and Calc). If this is not done, the payroll and absence calc will not process any data when the current pay period is finalized.
CHRS Security Roles
A Special Account has been created for this task. The information for that account is between CHRS Operations and HR/CHRS App Dev Team Members.
To complete these tasks, you need the following security roles assigned to your SSO account:
- CHR_AM_Calc_Absence_Payroll
- CHR_PT_Process_Admin
- CHR_AM_Central_Config
When to close and finalize the calendar
Calendars are finalized by CHRS Operations for the current month, and the calendar for the upcoming month is opened on the fifth business day. For example, in May 2024, the pay period (PP) begins on May 1st. The April 2024 calendar will be closed and the May 2024 calendar will be opened on May 7th.
On that day, wait for the 10:00 am recurrence to complete before proceeding.
To find when the Pay Period beings refer to the CSYOU Payroll Calendar.
- The green box that says 'PP Begins' is the first business day the pay period begins.
- Please note that if a 'Holiday' (blue box) falls when the 'PP Begins,' it should not be counted as a business day.
- Ex: July 2024, the 4th of July falls on a Thursday. The June calendar closing and July calendar opening will occur on Monday, July 8th.
Complete this procedure after the 10:00 am recurrence has completed.
You must be logged into CHRS with your Special Account.
Step 1: Open the Navbar button.

Step 2: Navigate to Menu > Global Payroll & Absence Mgmt > Absence and Payroll Processing > Calculate Absence and Payroll.
Step 3: Enter the Run Control ID CHRS-OPS, then click Search.

Step 4: Confirm that the Calendar Group ID and boxes under Processing Phases and Options are grayed out.
Step 5: Open Process Monitor.

Step 6: In Process Monitor, click the green recurrence icon for the CSUPYNLT process.
Step 7: In the Recurring Process/Job window,
- Click the Stop button.
- Click Return.
Recurrence is stopped. The current running process needs to be canceled.
Step 8: For the currently active CSUPYNLT process, click Actions > Update Process > Cancel Request.

Step 9: Click Refresh until the Run Status is Cancelled.

You have stopped CALC/RECALC and NLT recurrence.
Step 1: If you are still on the Process Monitor page, click Go back to Calculate Absence and Payroll.
- Otherwise navigate to Navigate to Menu > Global Payroll & Absence Mgmt > Absence and Payroll Processing > Calculate Absence and Payroll.

Step 4: On the Calculate Absence and Payroll page, do the following:
- Clear the Calculate and Recalculate All check boxes.
- Select the Cancel check box.
- Click Run
Step 5: On the Process Scheduler Request:
- Select GP & AM Payroll Job.
- Click OK.

Step 6: Open Process Monitor.

Step 7: Wait for the the run status to complete to success.

Step 1: If you are Process Monitor, click Go back to Calculate Absence and Payroll. Otherwise, navigate to Menu > Global Payroll & Absence Mgmt > Absence and Payroll Processing > Calculate Absence and Payroll

Step 2: Select the Calendar Group ID that you just cancelled.

- The calendar was not open because you ran the cancellation.
- Running Identify and Calculate reopens the calendar.
Step 3: Run the process with Identify and Calculate options.
- Select Identify and Calculate options.
- Click Run.
Step 4: On the Process Scheduler Request, select GP & AM Payroll Job, then click OK.
Step 5: Open Process Monitor.

Step 8: Wait for the the run status to complete to success.

Step 1: If you are Process Monitor, click Go back to Calculate Absence and Payroll. Otherwise, navigate to Menu > Global Payroll & Absence Mgmt > Absence and Payroll Processing > Calculate Absence and Payroll

Step 2: Select the current Calendar Group ID.

Step 3: Select Finalize, then click Run.
Step 4: On the Process Scheduler Request page, select the GP & AM Payroll Job, then click OK.
Step 5: Open Process Monitor.

Step 6: Wait for the the run status to complete to success.

Step 7: Log out of your Special Account.
You must be logged into CHRS with your normal SSO account.
Step 1: Open the Navbar button.

Step 2: Navigate to: Menu > Global Payroll & Absence Mgmt > Absence and Payroll Processing > Absence Conversion Processing > To Payroll for North America
Step 3: Select the Calendar Group ID that you just finalized.

If the month is not in the list, it did not successfully finalize. You must retrace your steps to ensure that the month finalized.
Step 4: Click Run.

Step 5: On Process Scheduler Request, click OK.
Step 6: Open Process Monitor.

Step 7: Confirm that the process ran to success.
You mus be logged into CHRS with your Special Account.
Step 1: Log in to CHRS with your Special Account (ask CHRS Operations for details).
Step 2: Open the Navbar button.

Step 3: Navigate to Menu > Global Payroll & Absence Mgmt > Absence and Payroll Processing > Calculate Absence and Payroll.
Step 4: Enter the Run Control ID CHRS-OPS, then click Search.

Step 5: Set up the run:
- Select the Calendar Group ID.
- Check the Identify and Calculate check boxes.
Step 6: Click Save.

Step 7: Click Run.

Step 8: On the Process Scheduler Request page,
- Select the GP & AM Payroll Job check box.
- Click OK.
Step 9: Open Process Monitor.

Step 10: Click Refresh until the Distribution Status is Posted.
- Verify that the Run Status was a Success.
Step 11. Click the link to Go back to Calculate Absence and Payroll.

Step 1: Set up Calculate and Recalculate run:
- Enter or confirm the Calendar Group ID is the same as the first run.
- Select Calculate and Recalculate All check boxes.
- Click Run.
Step 2: On the Process Scheduler Request page, set up the request:
- Set Recurrence to CSU Daily Every 2 Hours.
- Click Reset to Current Date.
- Verify that the Run Date is today's date.
- Select GP & AM Pay Calc/NLT Cleanup.
- Click OK.
Step 3: Open Process Monitor.

Step 4: Confirm that the CSUPYNLT process displays the recurrence icon (green circular arrow) next to the Process Name.

You have configured CALC/RECALC and NLP Recurrence for that calendar group.
End of Article
You are done. Great job!
0 Comments